Construction on the began Nov. 18 and is slated to run through summer 2025. During this time, there will be periods when sections of street parking will be blocked off on 9th and 10th Avenues along the north end of Central Campus and detours along the 16th Street corridor between 11th and 8th Avenues will be in place.
Anticipated impacts to parking and traffic flow near campus will change as the city moves through different phases of construction. The dates listed below are preliminary and will be updated as necessary.
Construction Impacts: Dec. 2 - Jan. 6
Campus Parking:
- Street parking along 9th and 10th Avenues near Skinner Music Library and Frasier Hall are expected to be open, but may see limited impacts. See shaded areas in orange on the map below.
Traffic Control:
- One-way westbound traffic on 16th St., between 9th and 11th Avenues. Eastbound traffic closed at 11th Ave.
- On-street parking along the north side of 16th St. will remain open. Parking on the south side of 16th St. will be closed.
- Traffic on 9th and 10th Avenues will be limited to north and south travel only in this area, access to 16th St. from 9th and 10th Avenues will be closed.
Construction Impacts: Jan. 6 - March 28
Campus Parking:
- Sections of street parking along 9th and 10th Avenues near Skinner Music Library and Frasier Hall will be blocked off. See shaded areas in red on the map below.
Traffic Control:
- One-way westbound traffic on 16th St., between 9th and 11th Avenues. Eastbound traffic closed at 11th Ave.
- No access to or from 9th or 10th Avenues to 16th St.
- On-street parking along the north side of 16th St. will remain open. Parking on the south side of 16th St. will be closed.
Construction Impacts: March 28 - April 25
Campus Parking:
- Sections of street parking along 9th and 10th Avenues near Skinner Music Library and Frasier Hall are expected to be open but may see limited impacts. See shaded areas in orange on the map below.
Traffic Control:
- One-way westbound traffic on 16th St., between 9th and 11th Avenues. Eastbound traffic closed at 11th Ave.
- On-street parking along the north side of 16th St. will be closed.
City of Greeley's 16th Street Enhancement Project
An artist's rendering of the future intersection of 16th Street and 10th Ave
The 16th Street Enhancement Project will create wider, even sidewalks and improve traffic safety along the 16th St. corridor. The new design will incorporate better landscaping and lighting and create more parking in the area.
According to the city, this first phase of construction is scheduled for the fall and winter as it requires underground work to the city’s utility lines. That work must be completed while the nearby irrigation ditch is dry and before it's used for spring operations. The city expects the majority of the aboveground work to roadways and parking will take place during summer break. The project is scheduled for completion in summer 2025.